According to the letter by BSNL’s GM (NWP-SP), Reena Malhotra, there’s a delay in installation and commissioning of core equipment in four zones by TCS, which could persist for an average of six months. This has resulted in a postponement of commissioning sites under the 4G saturation project.
BSNL argues that it’s proceeding with tower and passive infrastructure installation, enabling TCS to swiftly deploy eNBs upon equipment receipt.
Malhotra has urged DoT to consider this an “exceptional case” and compensate BSNL for the additional O&M cost at approximately Rs 55,000 per site for two quarters across roughly 9,000 impacted sites.
This request for Rs 99 crore reimbursement comes in the backdrop of the Centre approving a Rs 26,316 crore project in July 2022 to saturate 4G mobile services in uncovered villages across the country.
The project targets providing 4G connectivity in 24,680 uncovered villages in remote and difficult areas with the flexibility to include an additional 20% for various contingencies. Additionally, 6,279 villages with only 2G or 3G services will be upgraded to 4G. BSNL is executing this project with funding support from the USOF.
2024-09-20 03:15:17 Atalanta will kick off their UEFA Champions League campaign against Arsenal on Thursday…
2024-09-20 03:05:04 This is a developing story and will be updated. North Carolina Republican gubernatorial…
2024-09-20 02:55:03 AS Monaco faces FC Barcelona for Matchday 1 of the 2024-25 Champions League…
2024-09-20 02:45:03 19 de sep, 2024, 10:27 ETFlick no lo sabe, pero hay una sorpresa…
Apple cider vinegar, also known as ACV, has become a go-to drink for many in…
Kareena Kapoor Khan alone carried the film Jaane Jaan (2023) on her capable shoulders despite…